From empty land to the keys
Six steps, each with a clear owner, a timeline and a payment rule. Here is what happens, how long it takes and what we need from you.
Total: about 12–20 monthsincl. 2–4 months approvals
The six steps
- 01S-011–2 weeks
Free site visit & soil check
We walk your land with you. We check access, levels, drainage, neighbours and the soil, then tell you honestly what is possible and what it is likely to cost.
Your partBring your land title (geran) or a copy, and any family or loan plans.
- 02S-023–5 weeks
Design & fixed quotation
Pick one of our house designs or bring your own. Our draughtsman adjusts the layout to your lot. You get drawings, a full bill of quantities and one fixed price.
Your partChoose the layout and finishes. Sign the quotation when you are comfortable.
- 03S-032–4 months
Approvals (PBT / council)
We prepare and submit the building plans to your local council (PBT) through a registered Qualified Person, and chase every comment until approval. No site work starts before that.
Your partSign the submission forms. We handle the rest and update you every two weeks.
- 04S-046–12 months
Construction in seven stages
Site clearing, foundation, structure, roof and walls, M&E, finishing. You get weekly photo reports on WhatsApp and pay only after each stage passes a joint inspection.
Your partVisit any time with notice. Approve any variation in writing before it is built.
- 05S-054–8 weeks
CCC & handover
We clear the punch-list, apply for the Certificate of Completion and Compliance (CCC) and arrange utilities (TNB, Air Selangor, IWK). Then we hand you the keys.
Your partWalk the house with our supervisor and tick off the final list.
- 06S-0612 months
12-month defect liability
If a crack, leak or loose fitting shows up in the first year, call us. We come back and fix it at no cost. We also check in at month 6 without being asked.
Your partReport anything through WhatsApp with a photo. We respond within two working days.
PS-7Payment schedule
You pay in seven stages, never ahead of the work
The same percentages apply to every house, extension and small commercial build. Stage 1 is the only payment made before work on site begins. Try your own numbers below.
PS-7Progress payment schedule
Pay for work that is already there
Pick a type, size and finish to see what each stage payment would be. It uses the middle of the estimated range as the contract sum.
- Estimated range
- RM 266,000 – RM 329,000
- Contract sum used
- RM 298,000
- Build time
- 6.5–8.5 monthsplus 2–4 months for approvals
| Stage | % | Amount |
|---|---|---|
| 1Contract signingThe fixed-price contract is signed. Covers design, approvals and site set-up. | 10% | RM 29,800paid so far RM 29,800 |
| 2FoundationPiling or footings and ground beams are poured and pass a joint inspection. | 15% | RM 44,700paid so far RM 74,500 |
| 3StructureColumns, beams and floor slabs are complete and the concrete has been inspected. | 20% | RM 59,600paid so far RM 134,100 |
| 4Roof & wallsRoof trusses, roof covering and brickwork are complete. The house is weather-tight. | 20% | RM 59,600paid so far RM 193,700 |
| 5M&EPlumbing and electrical first-fix are complete and tested. | 15% | RM 44,700paid so far RM 238,400 |
| 6FinishingTiling, ceilings, doors, paint and fittings are complete. We issue the punch-list. | 15% | RM 44,700paid so far RM 283,100 |
| 7HandoverCCC is issued, keys are handed over and the punch-list is cleared. | 5% | RM 14,900paid so far RM 298,000 |
| Total | 100% | RM 298,000 |
Each payment is invoiced only after you have inspected the stage with our supervisor and signed the stage certificate. Loan lenders such as LPPSA and banks can pay against the same certificates. The final fixed price is set in your contract after the site visit.
JIJoint inspection
What we check before you pay
When a stage is finished, you (or someone you trust, such as a relative who knows construction) walk it with our site supervisor. Both of you sign the stage certificate.
Foundation
- Reinforcement size, spacing and cover
- Pile or footing depth against the design
- Concrete delivery note and cube samples
Structure
- Columns plumb and beams level
- Concrete cube test results
- Slab thickness and curing
Roof & walls
- Roof fixings and waterproofing
- Brickwork line and plaster quality
- Water test on the roof gutters
M&E and finishing
- Electrical test and earth continuity
- Pressure test on water pipes
- Tiles, paint and doors against the punch-list
A weekly report you can read in a minute
Every Friday, our site supervisor sends a short report to the homeowner on WhatsApp. This is a typical one.
Teguh Bina · Site report
Week 23 · Fri
- Done
- First-floor columns C1–C8 poured and stripped. Cube samples sent to the lab.
- Photos
- 14 attached, dated and grouped by area.
- Next
- Slab formwork and steel, Monday. Concrete pour planned for Thursday.
- Your OK
- Please choose porch tile A or B by Wednesday so the order is not delayed.
EXA real build
See the stages on the Kuang house
Photos from the double-storey home in Kuang, with the payment each stage released.
01Site clearing
Mar 2024

The lot was cleared and levelled in nine working days. Boundary pegs were checked against the land title by a licensed surveyor.
Payment 1 · 10% paid at signing
02Foundation
Apr 2024

Eighteen piles and pile caps, with a joint inspection of the reinforcement before the concrete pour. Stage 2 payment released that Friday.
Payment 2 · 15% after joint inspection
03Structure
Jun 2024

Ground-floor columns, beams and the first-floor slab. Concrete cube tests passed before the formwork came down.
Payment 3 · 20% after joint inspection
04Roof & walls
Sep 2024

Brickwork and roof trusses were completed in the same month, so the house was weather-tight before the monsoon.
Payment 4 · 20% after joint inspection
05Finishing
Jan 2025

Tiling, ceilings, painting, doors and kitchen cabinets. A punch-list of 41 small items was cleared in two weeks.
Payments 5 and 6 · 15% M&E, 15% finishing
06Handover
Nov 2025

CCC received, keys handed over. The family moved in the following week, in time for Hari Raya Haji planning.
Payment 7 · 5% after CCC
CCC Completion
CCC before you move in
The Certificate of Completion and Compliance (CCC) is the council’s confirmation that the house was built to the approved plans and is safe to occupy. We apply for it, handle the agencies (TNB, Air Selangor, IWK, Bomba where needed) and give you the original certificate. Your final 5% is released only after it is issued.
DLP Warranty
12 months, and we come back
A defect liability period starts on handover day. If a crack, a leak or a fitting fails because of our work, we repair it at no cost. We inspect with you at month 6 and month 12, and give you the warranty cards and as-built drawings on day one.
GOFree, no obligation
Book a free site visit
We walk your land with you, check the soil and access, and tell you honestly what is possible and what it will cost. You get a written note within three working days. Anywhere in Selangor and the Klang Valley.