A four-bedroom single-storey home for a schoolteacher using an LPPSA loan. Built from our Cempaka design in nine months, on the lot she inherited from her grandmother.

Location
Telok Panglima Garang, Kuala Langat
Type
Single-storey house
Built-up
1,780 sq ft
Handed over
June 2025
Time
9 months build + 4 months approvals
Fixed price
RM 342,000
Finished single-storey house with a wide car porch and a low pitched roof on a flat lot

Cikgu Hasnah inherited the 6,000 sq ft lot from her grandmother. The land was kampung land with an old title, so the first job was to confirm the lot boundaries, land use and any conditions before drawing a single line.

Our draughtsman adapted Cempaka to the plot, turned the porch to face the access road and moved the kitchen to the rear for better ventilation. PBT approval took four months, a little longer than usual because the council asked for extra drainage drawings.

The build ran to the schedule we gave in the contract. Payments followed the usual seven stages, and each stage certificate went straight to LPPSA for the next tranche.

Built from our Cempaka design(4 bedrooms, 1,760 sq ft before changes).

B/ABefore and after

The same lot

The finished single-storey house with a two-car porch on the same plot
Cleared flat plot of land with a fence and a dirt access road before building
A cleared kampung lot, and the same lot a year later

6Progress timeline

The build, stage by stage

The same weekly photos the homeowner received on WhatsApp. Each stage was inspected before its payment was released.

  1. 01Site clearing

    Aug 2024

    Cleared flat plot of land with a fence and a dirt access road before building

    A two-week site clearing and platform filling. We raised the levels by 600 mm to protect against seasonal flooding.

    Payment 1 · 10% paid at signing

  2. 02Foundation

    Sep 2024

    Timber formwork and steel bars for ground beams at a single-storey house site

    Ground beams and footings formed and inspected. The soil report showed soft clay, so we used spun piles as agreed in the contract.

    Payment 2 · 15% after joint inspection

  3. 03Structure

    Nov 2024

    Brick walls rising between reinforced concrete columns on a house under construction

    Columns, brickwork and ring beams. The brickwork was laid with the weekly photo report so the owner could check wall positions against the plan.

    Payment 3 · 20% after joint inspection

  4. 04Roof & walls

    Jan 2025

    Workers fixing concrete roof tiles on timber trusses of a single-storey house

    Timber trusses, concrete roof tiles and fascia. The house was weather-tight in 11 working days.

    Payment 4 · 20% after joint inspection

  5. 05Finishing

    Apr 2025

    Living room with a new plaster ceiling, recessed lights and a tiled floor before furniture

    Ceilings, tiles, doors and paint. The ensuite and kitchen tiles were chosen by the owner at our showroom visit.

    Payments 5 and 6 · 15% M&E, 15% finishing

  6. 06Handover

    Jun 2025

    Finished single-storey house with a wide car porch and a low pitched roof on a flat lot

    CCC issued, final inspection passed and keys handed over with the warranty cards and as-built drawings.

    Payment 7 · 5% after CCC

PS-7This contract

Paid in seven stages

The fixed price was RM 342,000. This is what the homeowner paid at each inspected stage. Nothing was paid ahead of the work.

Stage payments for this contract
Stage%Amount
1Contract signing10%RM 34,200
2Foundation15%RM 51,300
3Structure20%RM 68,400
4Roof & walls20%RM 68,400
5M&E15%RM 51,300
6Finishing15%RM 51,300
7Handover5%RM 17,100
Total100%RM 342,000
“I am a teacher, not a builder, and I did not know where to begin. They explained the LPPSA process, drew up the documents and kept every promise on the payment schedule. The house was ready before the school holidays.”
Cikgu Hasnah · Homeowner, Telok Panglima Garang

GOFree, no obligation

Book a free site visit

We walk your land with you, check the soil and access, and tell you honestly what is possible and what it will cost. You get a written note within three working days. Anywhere in Selangor and the Klang Valley.

WhatsAppFree site visit