A start-up logistics company needed a warehouse on a light-industrial plot in Klang and had a hard date for its first customer. We designed backwards from that date: structure first, approvals in parallel and the office fit-out last.
A steel portal frame is quick to put up, so the programme was driven by the foundation and the floor slab, which has to cure properly. We poured the floor in two phases, with an inspection and a flatness check after each.
Small commercial builds follow the same seven-stage payment schedule as our houses, with the fire-fighting system and Bomba approval added as extra milestones before handover.